Village Annual Street Project

Print
Press Enter to show all options, press Tab go to next option

Village Annual Street Project

Print
Press Enter to show all options, press Tab go to next option

2017 Street Revitalization Project

The Village is scheduled to begin work on segments of 26 streets this year.  Eight segments will be reconstructed and eighteen others will be resurfaced.  Click below for a list and map of the street segments to be completed as part of the 2017 project.

2017 Street Revitalization Project List
2017 Street Revitalization Project Map
2017 Street Revitalization Project Apron Contractor Information
Ash Road Modifications Plan
Construction Times Newsletter
Glen Lake Phasing Map

New!  Project Update - Week of July 24th
** Please note the changes to the tentative start dates on Bison Lane, Caribou Lane, Dukesberry Lane, Falcon Lane, Forbs Avenue and Newcastle Lane Phase I listed in the Project Schedule Update below.

Aberdeen Street:  Pavement grinding is expected to start at the end of the week.  Backfilling with topsoil and placement of grass seed and blanket is anticipated to start at the beginning of the week.

Ash Road:  Ditch grading work may also occur sometime during the week.

Bison Lane:  Storm sewer work is anticipated to start at the beginning of the week. Concrete replacement work will occur at the end of the week.

Cardigan Place:  Pavement striping work will occur toward the end of the week.

Caribou Lane:  Storm sewer work is anticipated to start at the beginning of the week. Concrete replacement work will occur at the end of the week.

Chandler Lane:  Storm sewer work is anticipated to begin at the beginning of the week. Concrete replacement work is anticipated to begin at the end of the week.

Falcon Lane:  Storm sewer work is anticipated to start at the beginning of the week. Concrete replacement work will occur at the end of the week.

Forbs Avenue:  Sawcutting is anticipated to occur throughout the week.

Gannon Court:  Pavement striping work will occur toward the end of the week.  Backfilling with topsoil and placement of grass seed and blanket will occur at the beginning of the week.

Glendale Lane:  Pavement grinding is expected to start at the end of the week.  Backfilling with topsoil and placement of grass seed and blanket is anticipated to start at the beginning of the week.

Glen Lake Road All Phases:  General cleanup will occur throughout the week.

Milton Lane:  Pavement striping work will occur toward the end of the week. 

Newcastle Lane Phase I (Oakmont Rd to Kingsdale Rd):  Pavement grinding work is anticipated to begin by the end of the week.  Concrete removal is anticipated to start at the end of the week.

Newcastle Lane Phase II (Kingsdale Rd to Fairmont Rd):  General cleanup will occur throughout the week.

Payson Street:  Pavement striping work will occur toward the end of the week. 

**Additional Paving Information**
- Binder Course (1st Layer of Asphalt – reconstruction streets only) – Paving signs are placed at the ends of the street on the day prior to asphalt installation.  This layer does not require oil application prior to paving as paving occurs on the stone base.

- Level Binder Course (1st Layer of Asphalt – resurfacing streets only) – Fresh Oil Signs are placed at the ends of the street between 12-24 hours prior to oil application (signs are placed on Friday prior to a Monday morning oil application).  Oil is typically placed in the early morning hours and level binder pavement is placed later that day (all work is weather dependent).  Paving signs are also placed at the ends of the street on the day prior to any asphalt installation.

- Surface Course (Final Layer of Asphalt – all streets) - Fresh Oil Signs are placed at the ends of the street between 12-24 hours prior to oil application.  Oil is typically placed in the early morning hours and final surface pavement is placed later that day (all work is weather dependent).  Paving signs are also placed at the ends of the street on the day prior to surface asphalt installation.

Remember cell phone use is prohibited in construction work zones and as always, please proceed with caution while driving in work zones.

If you have any questions about the 2017 Street Project, or if you would like to be added to the list to receive weekly project updates, please email roadconstruction@hoffmanestates.org with the words "2017 Street Project" in the subject line or call the Transportation and Engineering Division at 847-252-5800.

 

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer